SuvTrack guide
Everything in one place, for printing or reading on the phone. Choose your role; the “?” button inside the application shows the same steps page by page.
Contractor surveyor
You see the protocols of your own organisation only. Your work: open a protocol at the site, fill Phase A, submit it; later Phases B and C.
Protocol register
-
Start a protocol
Press “New protocol”, find the site, press “Open”. One protocol per meter at a site.
-
Find a protocol
Type the site reference (B-3674), the Meter ID or the facility name. The table filters as you type.
-
Narrow the list
Region, District, Facility type, the state of each phase and the Updated period combine. “Clear filters” resets.
-
Read the phase badges
A, B and C show each phase: draft, submitted, approved or rejected. Rejected means: open the protocol and read the comment.
-
See them on the map
“List + map” or “Map” places every protocol. Click a pin for its card; “List follows map” narrows the table to the visible area.
New protocol: choose the site
-
Find the site
Type the site reference from the site database (B-3674) or the facility name as written there. The list narrows as you type.
-
Or filter by place
Region and District narrow the picker to the area you work in. On a phone the filters sit behind “Filters”.
-
Check the pin
The map shows the matching sites. Click a pin to jump to its card and make sure it is the place you are standing at.
-
Open the protocol
On the card choose the meter number (1 for the first meter at this site) and press “Open”. An existing protocol opens instead of a duplicate.
Protocol form
Phase A
-
Read the box above Phase A
“How this form works” explains the three phases, the locks and the hold points in a minute.
-
Fill Phase A at the site
Sections A–F: the pipe, the existing meter, the chamber, the straight lengths. Grey cells are calculated for you; the example under a row shows the expected format.
-
Save often
“Save” keeps everything entered so far. “Unsaved changes” reminds you before you leave the page.
-
Watch the hold point
HP2 lights up when the measured pipe differs from the records or the straight lengths are short. Resolve it with the engineer before installation.
-
Submit Phase A for review
The button saves and checks the required entries; anything missing is listed with a link to the cell. After submission Phase A is read-only until a decision — “Withdraw” takes it back.
Phase B
-
Phase B: the installation design
Sections G and H open after Phase A is approved: the chosen meter, its position and the works. The selected meter model fills the technical values.
-
Submit Phase B
Same rule as Phase A: required entries first, then “Submit Phase B for review”.
Phase C
-
Phase C: commissioning
Section I after the meter is installed: the as-built position, the test readings and the result I6.
-
Submit Phase C
The last submission. An approved Phase C completes the protocol.
How this form works
- Three phases. A is the site survey (sections A–F), B the installation design (G, H), C the commissioning (I). Each is submitted and approved in turn.
- Locks. G and H open when A is approved; I opens when B is approved. A submitted or approved phase is read-only; “Withdraw” takes a submission back before the decision.
- Grey cells are calculated from your entries (the bore, the straight-length checks, the hold points). The example under a row shows the expected format.
- Hold points. HP2 turns on when the measured pipe differs from the records or the straight lengths are short: resolve it with the engineer before installation.
- Submitting checks the required entries and lists what is missing, with a link to each cell. Save often: “Unsaved changes” warns before you leave.
PMC and Uzsuvtaminot specialists
You see every protocol and may fill any phase. The same three-phase procedure applies; the register's filters and the map help to find a site quickly.
Protocol register
-
Start a protocol
Press “New protocol”, find the site, press “Open”. One protocol per meter at a site.
-
Find a protocol
Type the site reference (B-3674), the Meter ID or the facility name. The table filters as you type.
-
Narrow the list
Region, District, Facility type, the state of each phase and the Updated period combine. “Clear filters” resets.
-
Read the phase badges
A, B and C show each phase: draft, submitted, approved or rejected. Rejected means: open the protocol and read the comment.
-
See them on the map
“List + map” or “Map” places every protocol. Click a pin for its card; “List follows map” narrows the table to the visible area.
-
Export
“Export register (Excel)” downloads the filtered register with every value; the KML opens the sites in Google Earth.
New protocol: choose the site
-
Find the site
Type the site reference from the site database (B-3674) or the facility name as written there. The list narrows as you type.
-
Or filter by place
Region and District narrow the picker to the area you work in. On a phone the filters sit behind “Filters”.
-
Check the pin
The map shows the matching sites. Click a pin to jump to its card and make sure it is the place you are standing at.
-
Open the protocol
On the card choose the meter number (1 for the first meter at this site) and press “Open”. An existing protocol opens instead of a duplicate.
Protocol form
Phase A
-
Read the box above Phase A
“How this form works” explains the three phases, the locks and the hold points in a minute.
-
Fill Phase A at the site
Sections A–F: the pipe, the existing meter, the chamber, the straight lengths. Grey cells are calculated for you; the example under a row shows the expected format.
-
Save often
“Save” keeps everything entered so far. “Unsaved changes” reminds you before you leave the page.
-
Watch the hold point
HP2 lights up when the measured pipe differs from the records or the straight lengths are short. Resolve it with the engineer before installation.
-
Submit Phase A for review
The button saves and checks the required entries; anything missing is listed with a link to the cell. After submission Phase A is read-only until a decision — “Withdraw” takes it back.
Phase B
-
Phase B: the installation design
Sections G and H open after Phase A is approved: the chosen meter, its position and the works. The selected meter model fills the technical values.
-
Submit Phase B
Same rule as Phase A: required entries first, then “Submit Phase B for review”.
Phase C
-
Phase C: commissioning
Section I after the meter is installed: the as-built position, the test readings and the result I6.
-
Submit Phase C
The last submission. An approved Phase C completes the protocol.
Metering points
-
Find a point
Type the Meter ID (UZ-AND-BM-00012), the facility name or the Kobo id.
-
Filter the register
Lot, Region, District, Facility type, the existing meter, DN, material and the DB-01R contract flag combine. “Position to be checked” lists points with poor GPS.
-
Map view
“Map” clusters the points; zoom in and click a pin for its card. Full-screen is in the map's corner.
-
Export
CSV downloads the filtered rows; KML opens them in Google Earth. A point's page shows every survey value.
How this form works
- Three phases. A is the site survey (sections A–F), B the installation design (G, H), C the commissioning (I). Each is submitted and approved in turn.
- Locks. G and H open when A is approved; I opens when B is approved. A submitted or approved phase is read-only; “Withdraw” takes a submission back before the decision.
- Grey cells are calculated from your entries (the bore, the straight-length checks, the hold points). The example under a row shows the expected format.
- Hold points. HP2 turns on when the measured pipe differs from the records or the straight lengths are short: resolve it with the engineer before installation.
- Submitting checks the required entries and lists what is missing, with a link to each cell. Save often: “Unsaved changes” warns before you leave.
Protocol reviewers and managers
Besides filling, you decide the phases. “Awaiting my review” is your queue; the decision controls sit next to each phase title in the form.
Review queue
-
The queue
You see every protocol with a phase waiting for your decision. Untick the chip to go back to the whole register.
-
Open the submitted phase
The badge “Submitted” marks the phase to check. Open the protocol: the submitted phase is read-only for the author now.
-
Decide in the form
In the protocol, next to the phase title: choose Approved, Approved with comments or Rejected, write the comment (required to reject) and press Set.
Protocol form
Phase A
-
Read the box above Phase A
“How this form works” explains the three phases, the locks and the hold points in a minute.
-
Fill Phase A at the site
Sections A–F: the pipe, the existing meter, the chamber, the straight lengths. Grey cells are calculated for you; the example under a row shows the expected format.
-
Save often
“Save” keeps everything entered so far. “Unsaved changes” reminds you before you leave the page.
-
Watch the hold point
HP2 lights up when the measured pipe differs from the records or the straight lengths are short. Resolve it with the engineer before installation.
-
Submit Phase A for review
The button saves and checks the required entries; anything missing is listed with a link to the cell. After submission Phase A is read-only until a decision — “Withdraw” takes it back.
-
Decide Phase A
Next to the phase title: choose the decision, write the comment (required to reject) and press Set. Sections G and H unlock on approval.
Phase B
-
Phase B: the installation design
Sections G and H open after Phase A is approved: the chosen meter, its position and the works. The selected meter model fills the technical values.
-
Submit Phase B
Same rule as Phase A: required entries first, then “Submit Phase B for review”.
-
Decide Phase B
Approval of Phase B unlocks section I (commissioning). Reopening Phase A later returns B and C to draft.
Phase C
-
Phase C: commissioning
Section I after the meter is installed: the as-built position, the test readings and the result I6.
-
Submit Phase C
The last submission. An approved Phase C completes the protocol.
-
Decide Phase C
Check I6 against the tolerance before approving. The protocol is complete when Phase C is approved.
Protocol register
-
Start a protocol
Press “New protocol”, find the site, press “Open”. One protocol per meter at a site.
-
Find a protocol
Type the site reference (B-3674), the Meter ID or the facility name. The table filters as you type.
-
Narrow the list
Region, District, Facility type, the state of each phase and the Updated period combine. “Clear filters” resets.
-
Read the phase badges
A, B and C show each phase: draft, submitted, approved or rejected. Rejected means: open the protocol and read the comment.
-
See them on the map
“List + map” or “Map” places every protocol. Click a pin for its card; “List follows map” narrows the table to the visible area.
-
Export
“Export register (Excel)” downloads the filtered register with every value; the KML opens the sites in Google Earth.
-
Your review queue
“Awaiting my review” keeps only the protocols with a phase submitted to you. The number on the chip is the queue.
How this form works
- Three phases. A is the site survey (sections A–F), B the installation design (G, H), C the commissioning (I). Each is submitted and approved in turn.
- Locks. G and H open when A is approved; I opens when B is approved. A submitted or approved phase is read-only; “Withdraw” takes a submission back before the decision.
- Grey cells are calculated from your entries (the bore, the straight-length checks, the hold points). The example under a row shows the expected format.
- Hold points. HP2 turns on when the measured pipe differs from the records or the straight lengths are short: resolve it with the engineer before installation.
- Submitting checks the required entries and lists what is missing, with a link to each cell. Save often: “Unsaved changes” warns before you leave.
- Reviewers: the decision controls sit next to each phase title — choose Approved, Approved with comments or Rejected, write the comment (required to reject) and press Set. Reopening an approved phase returns it (and the later phases) to draft.
Everyone
Language, theme, the help drawer and the phone shortcut.
SuvTrack
-
Modules
The left bar lists the modules you may use. A red badge counts what waits for you.
-
Language
UZ, RU, EN or CN: the interface switches at once and remembers your choice on this device.
-
Light or dark
Toggle the theme. Dark is easier on the eyes in the field at night.
-
This help
Open “?” on any page for its procedure. “Restart tour” replays the introduction.
On the phone: add SuvTrack to the home screen
Chrome on Android
- Tap the ⋮ menu in the top-right corner of Chrome.
- Choose “Add to Home screen” (or “Install app”).
- Confirm with “Add”. The SuvTrack icon appears on the home screen and opens full-screen.
Safari on iPhone
- Tap the Share button (the square with an arrow) at the bottom of Safari.
- Scroll down and choose “Add to Home Screen”.
- Tap “Add”.
Programme (Dastur)
The programme layer of Loan 4582-UZB: the procurement packages, their contractual deadlines and the disbursement. Managers and administrators edit it; executives, coordinators and PMC staff read it.
- Packages: every tender package (CS-01 PMC, DB-01 and DB-02/03 bulk metering, GIS/AMS, CS-05, IT-01/02, NCS-01) with its PP v1 value, the six procurement steps, the key dates (plan / actual), the open issues and the next action. GAP is a pseudo-package for gender-action-plan tasks. Tasks and meetings carry a "Package" field, so the card lists them.
- RAG status: red — behind the PAM plan with a known blocker, amber — at risk or waiting on a decision, green — on track. A manager sets it on the package card; the dashboard counts the red ones and the register's chips filter by it.
- Contractual deadlines: notices, replies, payments and reports with their basis (e.g. GCC 17.1) and owner. Overdue ones are red, those within 14 days amber; the badge on "Dastur" counts both. Mark a deadline done when the obligation is met; a task can be started from it.
- Disbursement sources: the plan is PAM Table 12 (contract awards and ADB disbursement per quarter). Actual contract awards are recorded when a contract is signed; actual ADB disbursement comes from the ADB Client Portal export; the national statistics report (sheet Ozlashtirish_Stat) is imported from the Excel template and reconciled with the portal at each quarter end.